Catford station Access for All Improvements

As part of the Department for Transport’s Access for All programme, we have installed two new lifts at Catford Station, to provide step-free access between platforms. 

Part of the Government’s nationwide Railway Access for All Strategy, this £3.7 million scheme has made the station much easier to use for passengers with limited mobility, with luggage, bicycles or pushchairs.  

What work took place?

  • Installation of a link-bridge and two new lifts, one on each platform 
  • Installation of new CCTV cameras 

When did the work take place? 

The works started in January 2022 and completed in Summer 2023.  

I have a question about the project – how can I get in touch?

For more information call our National Helpline on 03457 11 41 41 or contact us on Twitter @NetworkRailSE.