Anglia structures

We are responsible for maintaining many structures which either support or cross the railway including road and rail bridges as well as pedestrian/cycle/equestrian bridges which provide safe access across the tracks.

Many structures date back to the Victorian period and require a lot of repair and maintenance to make sure they are fit for purpose. In some circumstances, the old structures may need a complete replacement to cope with modern demands.

Our engineers and maintenance teams plan works in advance to make sure the bridge structures continue to meet the demands of the railway and intersecting road network. This work can include:

  • refurbishment, which involves removing corrosion, repainting and resurfacing as well as replacing any lighting systems
  • strengthening, which involves welding new steel to a structure to improve its structural strength
  • replacement, which involves the full replacement of a life expired structure with a whole new bridge

Find out more about two LIVE projects in the Forest Gate and Brent areas:

List of significant structures work

Below is a list of significant structures work during this current five-year investment cycle, Control Period 7 (2024-2029), to ensure that we maintain the railway for current and future passengers.

Structure
Nature of project
Year of completion
Line

River Alde

Strengthening

2026

Regional Lines

River Deben Railbridge

Strengthening

2026

Regional Lines

Kingsbury Road

Replacement

Works Completed in 2024

London Overground

Stracey Road

Replacement

2026/27

London Overground

Talbot Road

Replacement

2026/27

London Overground

Strode Road

Replacement

2027/28

London Overground

Courtenay Road

Strengthening

2027/28

London Overground

Latimer Road

Replacement

2027/28

London Overground

Sceptre Road

Strengthening

2027/28

Great Eastern main line

Old Hydraulic Room

Strengthening

2028/29

Essex Thameside

Christian Street

Strengthening

2028/29

Essex Thameside

Chalkwell Avenue

Strengthening

2028/29

Essex Thameside

Kennedy Road

Replacement

Works completed in 2025

Essex Thameside

Downs Park Road

Replacement

Works completed in 2024

West Anglia main line

Bruce Grove

Strengthening

2027/28

West Anglia main line

Exmouth Place (Arch No. 368)

Strengthening

2027/28

West Anglia main line

Cutter Bridge

Strengthening

2028/29

West Anglia main line

The work listed above represents the most significant structures activities in our CP7 work bank which contains hundreds of planned minor activities that take place to maintain all our structures across the Anglia route. Please note all dates are subject to change.

Timelapse footage

Timelapse films by contractor Murphy showing replacement of life expired rail bridges at Christian Street and Morris Street (near Shadwell station) that carry the line out of Fenchurch Street station through East London and out to Essex. Completed during Christmas 2021.

Morris Street bridge

Christian Street bridge

Downs Park Road bridge

A film covering the work on the bridge in Hackney, which was completed at the end of 2024.

Neasden bridge

Timelapse film by contractor Murphy showing replacement of a life expired rail over rail bridge in North London during Christmas 2021.