Staines to Windsor improvement work
We carried out essential renewal work on the railway between Staines and Windsor & Eton Riverside to improve reliability for passengers
What did we do?
Between Monday 26 October and Sunday 1 November 2026 our engineers carried out essential maintenance and renewal work on the railway between Staines and Windsor & Eton Riverside.
These works help us continue to deliver a safer, more reliable railway for passengers.
Our main pieces of work during this blockade were:
- Renewing all 28 wheel timbers on Mustard Hill Bridge
- Renewing 30 long timbers (support multiple rails at junctions) in Datchet
- Refurbishing the switches and crossings at Staines
Why was it important we did this work?
The wheeltimbers (the large wooden blocks that carry the rails over bridges) on Mustard Hill bridge were old and would soon have been unable to support the fast and heavy trains that run over it. To run the railway safely, we would then have needed to reduce the speed of trains over the bridge, creating longer journeys and delays.
Renewing the wheeltimbers on the bridge meant that trains could continue to run quickly and safely over the bridge.
At Staines, renewing the switches and crossings (which allow trains to change tracks) will reduce the risk of delays caused by faulty equipment.
Why did we close the railway for a week?
Delivering this work as part of a single seven-day closure allowed us to complete multiple jobs at once, rather than closing the railway on repeated weekends. This meant less overall disruption for passengers and neighbours while upgrading the line to modern standards.
Safety, reliability and long-term resilience were at the heart of this programme, and we thank passengers and local communities for their patience while the work took place.