How major Derby upgrade completion benefits passengers

We’ve just handed back Derby station following a £200m project to enable faster and more reliable journeys.

The biggest investment in Derby’s railway – the Derby Resignalling Project – has completed after 79 days.

The work – part of the Midland Main Line Upgrade – included the remodelling of track and signalling systems, a new station platform and the extension of an existing footbridge.

Benefits

Before the upgrade, a complicated track layout at Derby constrained trains coming through the station. This regularly resulted in train services being held outside the station, waiting for a free platform or safe passage through.

How we prepared for the project