Cookies and networkrail.co.uk. We use cookies to give you the best experience on our website. If you continue, we'll assume that you are happy to receive them.
You can read more about how we use cookies, and turn them off, on this page.

  • Bath and North East Somerset (Bathnes)

  • Get the Flash Player to see this player.

    Network Rail’s 'orange army' lowered approximately 1 mile of track at Dundas Aqueduct to allow the line to be used as a diversionary route for freight trains in the future. This stunning time-lapse video shows the scale of the project and the level of work involved, while the work place in August 2015.

  • Last updated 8 July 2016. This page will be updated regularly.

    What we’re doing

    To enable the route to be electrified, we’re installing supporting masts and overhead lines, and preparing the foundations for these (‘piling’). We’ll also be modifying some of the bridges and other structures on the route to create the extra height needed for the overhead lines.

    Work dates and locations

    Piling work

    We're undertaking piling work between Keynsham and Brislington.  This will begin with a shift on Saturday 9th July and is expected to be ongoing every Saturday night for a further 9 weeks.  Weekend night shifts will be undertaken from 23:30hrs on Saturdays to 07:30hrs on Sundays.

    Further piling activities will then continue throughout the rest of the year. 

    Please rest assured that this work will only take place intermittently throughout 2016 and our website which is updated every week provides specific information, along with a detailed look ahead for the coming weeks. 

    Please note that this could change at short notice for operational reasons

    Residents Letter

    Somerset and Dorset Intersect Bridge Replacement

    Work to remove the central section of the bridge was safely completed at Christmas. We are currently waiting for the replacement section of the bridge to be manufactured. Once the new section is fitted, the bridge will be re-opened - currently planned for September 2016.   

    The nearby Bellotts Road Bridge will be closed between 09.00am - 4.00pm on Monday 25 and Tuesday 26 April 2016. This is to undertake preparation work ahead of parapet work due to take place later this year. 

    Somerset and Dorset residents letter  

    Keynsham Station

    Following the major engineering work at Keynsham Station during our TPOD (Temporary Period of Disruption) between April 2 and April 11 which involved lowering the track, remodelling the existing platforms and preparing the station for some other essential improvement work. We are now undertaking essential follow-up work to the station and we plan to complete the majority of our activities by September 2016.

    Keynsham residents letter

    St James Viaduct and Bath Spa Station

    We will be carrying out vegetation clearance and fencing off the area underneath the arches just off Rossiter Road, to be used as a material storage compound.

    In preparation for Bath Spa station to accommodate overhead electrification lines, we need to carry out structural investigations to assess the integrity of the brickwork at St James Viaduct.  We also need to undertake topographical surveys and ground investigation work throughout Bath Spa station.  See attached letter for more info.

    Public drop in sessions

    A number of bridges and structures along this route will be affected by the Great Western electrification programme.

    No road closures are scheduled yet.

    Please come and see our plans at the next session.

    Structure Drop-in session Closure date(s) Diversion Additional information
    All 4 July 2016 16:30 - 19:00     Brunswick Room,Guildhall, Bath, BA1 5AW
    All 2 August 2016 16:30 - 19:00     Brunswick Room,Guildhall, Bath, BA1 5AW
    All 6 September 2016 16:30 - 19:00     Brunswick Room,Guildhall, Bath, BA1 5AW
    All 11 October  2016 16:30 - 19:00     Brunswick Room,Guildhall, Bath, BA1 5AW
    All 1 November 2016 16:30 - 19:00     Brunswick Room,Guildhall, Bath, BA1 5AW
    All 6 December 2016 16:30 - 19:00     Brunswick Room,Guildhall, Bath, BA1 5AW
  •  
  • Frequently asked questions

    Answers to your questions about electrification, the environment and more:

  • Bath project updates and FAQ

    Answers to your questions about the electrification through Bath:

  • Contact us

    If you have a question about our infrastructure, call our 24 hour helpline:

    03457 11 41 41

    or contact us online