• Timeline

  • North Cotswold Line timeline
    1  Summer 2009 Double track laid in Chipping Camden Tunnel
    2  Summer 2010 Preparatory work on track. 
    3  Autumn 2010 Honeybourne bridge replaced.
    4  Dec 2010 – May 2011 New double track laid, work carried out at night to minimise disruption
    5  28 May – 6 June Stage 1 complete – Charlbury to Ascott-under-Wychwood.
    6  6 – 22 August Stage 2 complete – Moreton-in-Marsh to Evesham.