Schemes in Development

Strategic Route No.Territory Scheme name Auth to GRIP Stage Standalone enhancement or undertaken with a planned renewal
1 SE Waterloo East second station entrance 4 Standalone
1 SE Shakespeare Tunnel clearance for high speed line service (Class 395) 4 Standalone
1 SE Crofton Road Junction remove approach control 4 Standalone
2 SE East Grinstead signalling improvements 4 Standalone
3 SE Barnes and Putney customer information system upgrade 3 Standalone
3 SE Eastleigh area signalling enhancements 4 Standalone
3 SE Brockenhurst turnback and bi-directional signalling 4 Standalone
4 SE Yeovil frequency improvements 4 Standalone
5 LNE Hitchin-Cambridge Junction ladder linespeed increase 1 Renewal
6 SE West Ham signalling enhancements 4 Standalone
7 SE Colchester subway reopening 1 Standalone
8 LNE Kettering South to Harrowden Junction additional third line 4 Standalone
8 LNE Bathley Lane level crossing overhead line electrification enhanced protection 1 Standalone
8 LNE Peterborough lineside renewals 4 Renewal
9 LNE Durham Coast shorten signal block section 3 Renewal
10 LNE Cliffe - Selby line speed increase 1 Standalone
10 LNE Church Fenton switch and crossing line speed increase 4 Renewal
11 LNE Woolley Coal Siding signal box enhancement 3 Standalone
13 W West Ealing Bay platform enhancement 1 Standalone
13 W Oxford down goods loop conversion to passenger status 4 Renewal
13 W Worle Junction to Weston upgrade 2 Renewal
13 W Oxford up goods loop conversion to passenger status 1 Renewal
14 W Shrewsbury Station Platform 3 enhancements 3 Standalone
15 W Ninian Park to Radyr linespeed enhancement GRIP Stage 3 feasibility 2 Renewal
17 LNW Wolverhampton - Shrewsbury linespeed improvements (part of Wolverhampton resignalling) 3 Standalone
17 LNW Cannock linespeed Improvements 3 Standalone
17 LNW Birmingham - Cross city north linespeed improvements 3 Standalone
17 LNW Bromsgrove Station platform relocation 4 Standalone
17 LNW Birmingham New Street platform 12 second pedestrian access 3 Standalone
17 LNW Water Orton enhancements 5 Renewal
17 LNW Walsall-Bescot resignalling 4 Renewal
18 LNW Northampton Depot 2nd access 4 Standalone
18 LNW Wembley Central platform extension 3 Standalone
19 LNE Chesterfield new platform 3 Standalone
19 Cross Peterborough - Nuneaton gauging improvements 4 Standalone
19 LNE Robin Hood Line performance improvements 4 Standalone
19 LNE Leicester - Syston - Trent South line speed increase 3 Standalone
19 LNE Flashing yellows at Radlett Junction, Harpenden Junction and Leagrave 2 Standalone
19 LNE Luton Station re-development 2 Standalone
19 LNE East Midlands - resignalling Nottingham Station 2 Renewal
20 LNW Manchester Piccadilly Station - Enhancements to Platforms 13 and 14 4 Standalone
20 LNW Salford Crescent - passenger capacity and additional platform 2 Standalone
21 LNW Liverpool Station capacity improvements 1 Standalone
22 W Blaenau Ffestiniog freight line enhancement 3 Standalone
24 SC Bishopbriggs platform extension 3 Standalone
24 SC Grangemouth Branch improvements 1 Standalone
24 SC Stirling middle switch and crossing renewal 3 Renewal
24 SC Ladybank/Hilton linespeed improvements - Phase 1 2 Renewal
24 SC Newbridge switch and crossing renewal 2 Renewal
26 SC Ayrshire coal routes: Kilmarnock rounding facility 4 Standalone
26 SC Eglington Station - feeder station enhancement 5 Renewal
26 SC Dumfries Station improved turnback facility 4 Renewal
Multi Cross Southampton - West Coast Main Line gauge enhancements 5 Standalone
Multi SE Class 376 regenerative braking 4 Standalone
Multi SE Hackney Interchange upgrade 4 Standalone
Multi Cross Felixstowe - Nuneaton capacity improvements 3 Standalone
Multi SC Greenhill area signalling renewals 3 Renewal
Multi W Cardiff area resignalling renewal 5 Renewal

 Key:

GRIP stage : Describes how Network Rail manages and controls projects that enhance or renew the national rail network.  It covers the project process from inception through to the post implementation realisation of benefits.

Standalone enhancement : An enhancement undertaken as a separate scheme independent of any planned renewal.

Enhancement undertaken with a renewal : An enhancement implemented as part of a planned renewal.