Key Milestones

 Key Milestones

February 2007

Office of Rail Regulation (ORR) publishes its ‘Advice to ministers and framework for setting access charges’

July 2007

Secretary of State for Transport and Scottish Ministers publish their high level output specifications (HLOSs) and statements of public funds available (SoFAs)

October 2007

Network Rail completes its Strategic Business Plan (SBP), including indicative levels of individual access charges

November 2007

ORR launches a public consultation on the SBP

December 2007

ORR completes its initial assessment of whether the HLOSs can be delivered for the available public funds

February 2008

ORR publishes its assessment of the SBP, including decisions on the financial framework following the August 2007 consultation and decisions on the early start programme for 2009-10

April 2008

Network Rail makes any necessary revisions to the SBP

June 2008

ORR publishes its draft determinations for Control Period 4 (CP4; which runs from 2009-2014), marking the start of a 12-week consultation period

August 2008

Network Rail responds to ORR draft conclusions

October 2008

ORR publishes its final determinations for CP4

December 2008

Final access charges (price lists/charge schedules) are audited and approved and a review notice is served starting the implementation of Periodic Review 2008

February 2009

Final point at which objections could be made to ORR’s review notice starting implementation, leading to a revised notice or possible Competition Commission reference

March 2009

Network Rail publishes its CP4 business plan