• Standard suite of contracts

  • It is our intention to always engage our contractors and suppliers on the basis of the following standard contracts.

    These contracts were developed following discussions with various industry bodies and many issues raised were incorporated in the final drafting. We believe our standard suite of contracts reflect a sensible allocation of risk and responsibility between the parties and that these contracts will save management time for us and our suppliers and contractors when setting up and managing contracts.

    Suppliers and contractors should always submit tenders that are compliant with the appropriately selected contract but, subject to meeting this requirement, may offer alternative tenders where this provides demonstrable benefits to Network Rail.

    Contract reference Version, release date Form of contract Comments:
    NR1   1.8
    Aug 11
    Purchase of Goods Version 1.8 includes ours anti-bribery clause and QA Classification of Products.
    NR1(S)   1.5
    Aug 11
    Purchase of Goods – Purchase Order version Version 1.5 includes our clause on QA Classification of Products and anti-bribery clause.
    NR2   1.0
    Jan 12
    Purchase of Services New form for non-construction professional services.
    NR2(S)   1.5
    Aug 11
    Purchase of Services Version 1.5 includes our anti-bribery clause and 28 day payment from agreed invoice.
    NR3   3.1
    Jan 12
     
    Construction & Engineering Services Agreement

    V3.1 includes Project Insurance, 21 day payment from application, Construction Act changes and updates the Contract Requirements HSQE.

    NR4   2.3
    Jan 12
    Short Form Works Contract Version 2.3 includes Project Insurance, 21 day payment from application and other minor changes (Construction Act changes to follow).
    NR4(MT)   2.3
    Jan 12
    Measured term version of NR4 Version 2.3 includes Project Insurance, 21 day payment from application and other minor changes (Construction Act changes to follow).
    NR5   1.3
    Aug 11
    General conditions of contract for the sale of used materials and equipment Version 1.3 includes our anti-bribery clause.
    NR6   2.1
    Feb 10
    Operation and maintenance of non Network Rail plant and equipment New contract. Version 2.1 represents a significant re-write and simplification of the previous version of this contract.
    NR7   2.3
    May 10
    Operation and maintenance of on-track plant New contract. Version 2.3 corrects a minor referencing error in clause 14.5.
    NR8   2.3
    Jan 12
    ICE Measurement version 7th edition (Jan 2003 incorporating July 2004 amendments) (Remeasurement contract) Version 2.3 includes Project Insurance, 21 day payment from application and Construction Act changes.
    NR9   2.4
    Jan 12
    ICE Design & Construct 2nd Edition (September 2001 incorporating October 2001 and July 2004 amendments) (Lump sum contract)

    Version 2.4 includes Project Insurance, 21 day payment from application and Construction Act changes.

    NR10   2.2
    Jan 12
    JCT 05 Design & Build (2005 Edition) (Lump sum contract) Version 2.2 incl. Project Insurance, 21 day payment from application and other minor changes (Construction Act Changes to follow shortly).
    NR11   2.0
    Jan 12
    MF/1 Rev 4 (2000 Edition) (Lump sum contract)

    V2.0 incl Project Insurance, 21 day payment from application and many other changes (Construction Act Changes to follow shortly).

    NR12   2.4
    Jan 12
    ICE Target Cost (February 2006 Edition) incorporating design (Reimbursable contract) V2.4 incl. Project Insurance, 21 day payment from application and Construction Act changes.
    NR12(A)  

    2.3
    Jan 12

    ICE Target Cost (February 2006 Edition) (Reimbursable contract) V2.3 incl. Project Insurance, 21 day payment from application and Construction Act changes.
    NR13(A)   1.4
    Aug 11
    Framework Contract for Goods Version 1.4 includes our anti-bribery clause.
    NR13(B)   1.4
    Aug 11
    Framework Contract for Services Version 1.4 includes our anti-bribery clause.
    NR13(C)   1.4
    Aug 11
    Framework Contract for Works Version 1.4 includes our anti-bribery clause.
    NR14   2.1
    Jan 12
    JCT SBC 2005 with Quantities (Lump sum contract) V2.1 incl Project Insurance, 21 day payment from application and many other changes (Construction Act Changes to follow shortly).
    NR15   2.5
    Jan 12
    MF/2 Rev 1 (1999 Edition) (Lump sum contract)

    Version 2.5 includes 28 day payment from invoice and other minor amendments.

    NR16   1.1
    Aug 11
    Provision of Labour Services Version 1.1 includes our anti-bribery clause and corrects some minor errors.
    NR18   1.2
    Aug 11
    Design, modification, refurbishment and servicing of Rail Vehicles

    Version 1.2 includes our anti-bribery clause and corrects some minor issues.


    Supporting documents

    Contract Requirements HSQE - Works version 1.7
    Parent Company Guarantee
    Parent Company Guarantee for Frameworks
    Collateral Warranty - Consultant
    Collateral Warranty - Construct Only
    Collateral Warranty - Design and Construct
    Vesting Certificate 

    If you require further information on our forms of contract, please email ContractsEvaluation@networkrail.co.uk