    Our plans for Paddington station

  • paddington  timeline
    1  Early 2009 - work starts on the roof and platform restoration.
    2  January 2010 - Demolition of taxi ramp to make room for the construction of the new Hammersmith & City Underground station.
    3  Summer 2011 - Completion of roof and platform restoration work.
    4  Winter 2012 - Completion of new Hammersmith & City Underground station.
    5  Winter 2012 - Construction of the Crossrail station starts.
    6  2017 - Completion of work on the Crossrail station.