  • Timeline for King's Cross redevelopment

  • King's Cross - timeline
     

    1  November 2007: Network Rail obtains full planning permission for station redevelopment
    2  March 2009: refurbishment of the Eastern Range building complete
    3  December 2009: London Underground ticket hall opens
    4  May 2010: new platform (platform 0) under the Eatern Range opens
    5  19 March 2012: new concourse opens
    6  July 2012: restoration of Victorian roof complete
    7  September 2012: removal of old concourse and start of work on square
    8  Winter 2013: new public square opens marking project completion