• Indicative timeline for the project

  • Timeline Redditch
    1  20 April 2012: Consultation starts
    2  28 May 2012: Deadline for consultation responses
    3  Summer 2012: Application submitted
    4  Autumn/winter 2013: Application determined
    5  Winter 2013: Construction starts
    6  Spring 2014: New track opens
    7  Winter 2014: Landscaping work complete